Project: Greg's_RV-10   -  
            Listing of Entries
    (Please mouse-over any icon to get a description of that function).


  
Builder Name:Greg Kochersperger   -  
Project:   Vans - RV-10
Total Hours:1320.9
Total Flight Time:1.1
Start/Last Date:Jan 15, 2021 - No Finish Date
Engine:IO-540
Propeller:TBD
Panel:Garmin G3X
 
Friendly URL: https://eaabuilderslog.org?s=Greg's_RV-10

Home or Last Project Picture

Mar 15, 2023     25-7: Priming and dimpling - (7.0 hours)       Category: 26: Fuse Ribs
Prepped and primed the bottom skins and stiffeners. Started dimpling the bottom skins in the DRDT2.

3/16: finished dimpling both bottom skins. Cleared off the bench to set the skeleton upright on it to prepared for dimpling - it's too tall! Measure the width and check against the cradle; it's just the right width to support the rear fuselage upright and a little closer to the ground. It even balances on the flange but I clamped it down for good measure.

Started dimpling the substructure.

3/17: finished dimpling the substructure and the footwell stiffeners. Then fluted the stiffeners. Countersunk the holes in the aft spar and all the holes coincident with tabs. Then the big moment - cleco'd the bottom skins on the frame. That's about as far as I can take this section until I get a riveting partner for the skin.

3/19: well anal retentive me remembered that I planned to put Ekopoxy in the tunnel. So I proceeded to uncleco everything and masked off the tunnel and spar area to overcoat in Ekopoxy.


 